JJM PWS Scheme analysis as per different stages of work
Format PM-18
SNo State/ UT Total Schemes# Number of schemes
Physically completed Scheme commissioned Financially completed Scheme not physically completed
Total Civil work not yet completed Civil work completed but awaiting electrification Civil work and electrification completed, but trial run pending Civil work, electrification, and trial run completed
A B C D (Out Of C) E (Out Of C) F= (G + H + I + J) G H I J
Total 638550 395159 242408 114255 243391 201373 7686 14260 20072
1 Andaman & Nicobar Islands 40 25 24 24 15 10 0 4 1
2 Andhra Pradesh 76068 14412 8246 1200 61656 55726 117 906 4907
3 Arunachal Pradesh 7152 6697 5290 5249 455 237 0 207 11
4 Assam 96006 82145 72812 29305 13861 12445 132 984 300
5 Bihar 304 302 300 301 2 2 0 0 0
6 Chhattisgarh 32215 15311 5589 122 16904 15707 315 186 696
7 Goa 256 256 244 243 0 0 0 0 0
8 Gujarat 585 371 319 308 214 50 2 161 1
9 Haryana 6558 6194 5130 3687 364 345 5 12 2
10 Himachal Pradesh 1747 1133 821 808 614 465 15 123 11
11 Jammu & Kashmir 3361 1468 732 20 1893 1456 58 367 12
12 Jharkhand 97535 67065 31347 2665 30470 29562 75 266 567
13 Karnataka 66318 44745 28363 25314 21573 12125 959 2312 6177
14 Kerala 1730 272 126 43 1458 1216 9 214 19
15 Ladakh 414 364 276 57 50 44 1 4 1
16 Lakshadweep 10 4 0 0 6 5 0 1 0
17 Madhya Pradesh 45111 32967 15983 3312 12144 9557 1305 978 304
18 Maharashtra 51558 25476 12477 7073 26082 17778 1510 3585 3209
19 Manipur 1266 532 54 54 734 434 5 238 57
20 Meghalaya 7790 6222 2501 1670 1568 804 49 593 122
21 Mizoram 852 850 697 478 2 2 0 0 0
22 Nagaland 1408 1186 926 873 222 135 9 36 42
23 Odisha 15377 9586 7943 4754 5791 4878 134 115 664
24 Puducherry 91 26 0 0 65 65 0 0 0
25 Punjab 2307 2210 2111 1954 97 76 0 3 18
26 Rajasthan 11621 4849 2599 1644 6772 4327 1488 567 390
27 Sikkim 1791 1187 358 58 604 48 0 525 31
28 Tamil Nadu 21432 21304 18364 12666 128 117 2 5 4
29 Tripura 19637 12253 6435 2727 7384 6442 198 116 628
30 Uttar Pradesh 40955 19035 2812 419 21920 17840 1282 1037 1761
31 Uttarakhand 16555 15581 9059 6660 974 528 2 422 22
32 West Bengal 10500 1131 470 567 9369 8947 14 293 115
Total 638550 395159 242408 114255 243391 201373 7686 14260 20072
Note :
(1). Civil Work Completed: All structural components (intake structures, pump houses, treatment plants, service reservoirs, pipelines, etc.) are constructed and ready for equipment installation. Marked complete in JJM-IMIS.
(2). Electrified: Electrical infrastructure (power supply system, wiring, electrical panels) is installed for operating pumps, motors, and other components. Marked complete in JJM-IMIS. Not required for gravity-based schemes.
(3). Trial Run Completed: All equipment and machinery installed, and a trial run conducted to ensure proper functioning. System operates as intended. Marked complete in JJM-IMIS.
(4). Physically Completed : Entire water supply system (civil, electrical, mechanical works) is fully completed, operational, and ready for commissioning. Approved by the State Authority. Marked complete in IMIS.
(5). Scheme Commissioned: Water supply system is fully operational, meets design specifications, and performance standards. Ready for handover. Marked complete in JJM-IMIS with the commissioning date entered in IMIS.
(6). Financially Completed: All financial obligations related to the project are fulfilled. Marked complete in IMIS.
(7). # Only ongoing and completed JJM PWS schemes are counted here:.



×
Report header
Column description :