Skip Navigation LinksHome > Format PM18 - Scheme analysis as per diffrent stages of work
JJM PWS Scheme analysis as per different stages of work
Format PM-18
SNo State/ UT Total Schemes# Number of schemes
Physically completed Scheme commissioned Financially completed Scheme not physically completed
Total Civil work not yet completed Civil work completed but awaiting electrification Civil work and electrification completed, but trial run pending Civil work, electrification, and trial run completed
A B C D (Out Of C) E (Out Of C) F= (G + H + I + J) G H I J
Total 638550 394460 242358 113796 244090 201879 7717 14273 20221
1 Andaman & Nicobar Islands 40 25 24 24 15 10 0 4 1
2 Andhra Pradesh 76068 14412 8246 1200 61656 55726 117 906 4907
3 Arunachal Pradesh 7152 6658 5290 5128 494 260 0 212 22
4 Assam 96006 82121 72809 29305 13885 12456 132 985 312
5 Bihar 304 302 300 301 2 2 0 0 0
6 Chhattisgarh 32215 15302 5587 122 16913 15747 316 186 664
7 Goa 256 256 244 243 0 0 0 0 0
8 Gujarat 585 371 319 308 214 50 2 161 1
9 Haryana 6558 6194 5130 3687 364 345 5 12 2
10 Himachal Pradesh 1747 1133 821 808 614 483 12 108 11
11 Jammu & Kashmir 3361 1468 732 20 1893 1456 58 367 12
12 Jharkhand 97535 67034 31347 2441 30501 29589 75 270 567
13 Karnataka 66318 44390 28355 25314 21928 12219 970 2322 6417
14 Kerala 1730 272 126 43 1458 1224 9 212 13
15 Ladakh 414 364 276 57 50 44 1 4 1
16 Lakshadweep 10 4 0 0 6 5 0 1 0
17 Madhya Pradesh 45111 32933 15964 3312 12178 9586 1307 985 300
18 Maharashtra 51558 25476 12477 7073 26082 17788 1511 3587 3196
19 Manipur 1266 532 54 54 734 448 5 239 42
20 Meghalaya 7790 6220 2494 1609 1570 804 49 593 124
21 Mizoram 852 850 697 478 2 2 0 0 0
22 Nagaland 1408 1186 926 873 222 138 10 36 38
23 Odisha 15377 9566 7944 4753 5811 4906 134 115 656
24 Puducherry 91 26 0 0 65 65 0 0 0
25 Punjab 2307 2210 2111 1954 97 76 0 3 18
26 Rajasthan 11621 4836 2599 1643 6785 4331 1495 567 392
27 Sikkim 1791 1187 358 58 604 48 0 525 31
28 Tamil Nadu 21432 21304 18364 12615 128 117 2 5 4
29 Tripura 19637 12087 6426 2727 7550 6590 209 117 634
30 Uttar Pradesh 40955 19035 2809 419 21920 17886 1282 1036 1716
31 Uttarakhand 16555 15581 9059 6660 974 528 2 422 22
32 West Bengal 10500 1125 470 567 9375 8950 14 293 118
Total 638550 394460 242358 113796 244090 201879 7717 14273 20221
Note :
(1). Civil Work Completed: All structural components (intake structures, pump houses, treatment plants, service reservoirs, pipelines, etc.) are constructed and ready for equipment installation. Marked complete in JJM-IMIS.
(2). Electrified: Electrical infrastructure (power supply system, wiring, electrical panels) is installed for operating pumps, motors, and other components. Marked complete in JJM-IMIS. Not required for gravity-based schemes.
(3). Trial Run Completed: All equipment and machinery installed, and a trial run conducted to ensure proper functioning. System operates as intended. Marked complete in JJM-IMIS.
(4). Physically Completed : Entire water supply system (civil, electrical, mechanical works) is fully completed, operational, and ready for commissioning. Approved by the State Authority. Marked complete in IMIS.
(5). Scheme Commissioned: Water supply system is fully operational, meets design specifications, and performance standards. Ready for handover. Marked complete in JJM-IMIS with the commissioning date entered in IMIS.
(6). Financially Completed: All financial obligations related to the project are fulfilled. Marked complete in IMIS.
(7). # Only ongoing and completed JJM PWS schemes are counted here:.



×
Report header
Column description :